Match List – I (Methods) with List –II (Applications) and select the correct answer using the codes given below the lists :
List – I
A. Break even analysis
B. Transportation problem
C. Assignment problem
D. Decision tree
List – II
1. To provide different facility at different locations
2. To take action from among the paths with uncertainty
3. To chose between different methods of manufacture
4. To determine the location of the additional plant
Option (A)
ABCD
4312
Option (B)
ABCD
3412
Option(C)
ABCD
3421
Option(D)
ABCD
4321
Correct Option:
(B)
Question Solution:
(a) Break even analysis: To choose between different methods of manufacture
(b) Transportation problem : To determine the location of the additional plant
(c) Assignment problem : To provide different facility at different locations
(d) Decision tree: To take action from among the paths with uncertainty