Question:-
Match List - I with List – II and select the correct answer using
List - I (Term)
A. Dummy activity
B. Critical path
C. PERT activity
D. Critical path method
List -II (Characteristics)
1. Follows b distribution
2. It is built on activity-oriented diagram
3. Constructed only to establish sequence
4. Has zero total slack
Option (A)
ABCD
3412
Option (B)
ABCD
4231
Option(C)
ABCD
3421
Option(D)
ABCD
4213
Correct Option:
(A)