Question:-
Common Data Questions: 50 & 51

Four jobs are to be processed on a machine as per data listed in the table.






Job Processing time (in days) Due date
1 4 6
27 9
3219
48 17


Q. If the Earliest Due Date (EDD) rule is used to sequence the jobs, the number of jobs delayed is
Option (A)
1
Option (B)
2
Option(C)
3
Option(D)
4
Correct Option:
(C)