Question:-
Match List I (Activity) with List II (Technique) and select the correct answer using the code given below the Lists:
List I
A. Line Balancing
B. Product Development
C. Forecasting
D. Quality Control
List II
1. Value analysis
2. Exponential smoothing
3. Control chart
4. Selective control
5. Rank position matrix
Option (A)
ABCD
2143
Option (B)
ABCD
5321
Option(C)
ABCD
2341
Option(D)
ABCD
5123
Correct Option:
(D)