Question:-
Consider the following :
1. A mass production schedule
2. An inventory status file
3. Bill of material
Which of the above are the inputs to MRP systems ?
Option (A)
1, 2 and 3
Option (B)
1 and 2 only
Option(C)
2 and 3 only
Option(D)
3 only
Correct Option:
(A)