Question:-
Consider the above network. Activity times are given in number of days. The earliest expected occurrence time (TE) for event 50 is:

Option (A)
22
Option (B)
23
Option(C)
24
Option(D)
25
Correct Option:
(D)
Question Solution:

Critical path is given by 10-20-30-40-50
\ the earliest expected occurrence time (TE) for the event is 25.