Question:-
Consider the following statements in respect of PERT and CPM:
1. PERT is event-oriented while CPM is activity-oriented.
2. PERT is probabilistic while CPM is deterministic.
3. Leveling and smoothing are the techniques related to resource scheduling in CPM.
Which of the statements given above are correct?
Option (A)
1, 2 and 3
Option (B)
Only 1 and 2
Option(C)
Only 2 and 3
Option(D)
Only 1 and 3
Correct Option:
(B)