Question:-
Consider the following statements: PERT considers the following time estimates
1. Optimistic time
2. Pessimistic time
3. Most likely time
Which of the statements given above are correct?
Option (A)
1, 2 and 3
Option (B)
1 and 2 only
Option(C)
3 only
Option(D)
1 and 3 only
Correct Option:
(A)
Question Solution:
te = {(t0 + 4tm + tp) / 6}
Where
te = expected time
t0 = optimistic time
tm = most likely time
tp = pessimistic time