Question:-
Consider’ the following statements:
1. Preparation of master production schedule is an iterative process ‘
2. Schedule charts are made with .respect to jobs while load charts are made with respect to machines
3. MRP is done before master production scheduling
Which of the statements given above are correct?
Option (A)
1, 2 and 3
Option (B)
1 and 2
Option(C)
2 and 3
Option(D)
1 and 3
Correct Option:
(B)
Question Solution:
A MRP system basically consists of a computer program which converts inputs into output. The inputs to the MRP system are
(i) Master production schedule
(ii) Inventory status file
(iii) Bill of materials (BOM)
question-answer-faq-8824