Question:-
Match List - I with List - II and select the correct answer using the code given below the lists: List-I
A. Procurement cost
B. Carrying cost
C. Economic order quantity
D. Reorder point
List-II
1. Cost of holding materials
2. Cost of receiving order
3. Procurement lead time
4. Break-even analysis
Option (A)
ABCD
3142
Option (B)
ABCD
3412
Option(C)
ABCD
2143
Option(D)
ABCD
2413
Correct Option:
(C)
question-answer-faq-8888