Question:-
The proper sequence of activities for material requirement planning are
Option (A)
Master production schedule, capacity planning, MRP and. Order release
Option (B)
Order release, master production schedule, MRP arid capacity planning
Option(C)
Master production schedule, order release , capacity planning and MRP
Option(D)
Capacity planning, master production schedule, MRP and order release
Correct Option:
(A)